Question: b ) Based on the Q 1 demand - supply schedule, comment If the production managed to fully support all demand timely. You may restructure
b Based on the Q demandsupply schedule, comment If the production
managed to fully support all demand timely. You may restructure the table.
c The production executive has decided to replan the entire schedule in Q
Additional Information.
Assuming that by end W after realizing the production hiccups, the
production has ordered additional units to clear backlog.
II Demand forecasting can never be accurate. Hence the production
executive used the prevlous quarter's weeks moving average as
baseline for
III The productlon planner Intends to keep weekly units of safety stock.
Iv Demand for Q is based on the schedule below.
How should the production executive analyze the production schedule and
replan accordingly. You may tabulate your demandsupply Into approprlate
table that indicates:
Inventory on hand.
Supplydemand schedule.
Net requirement
Required safety stock.
The output should be a replan schedule into an approprlate table commonly
known as Master Production Schedule. Comment on your schedule.Question
Production planning requires responsive supply replenishment to demand
changes. Thls is especially acute in manufacturing or service Industry adopting
bulld to stock business model. It's a challenging task to analyze demand pattems
and strateglze supply schedules.
The following scenarlo Indicates a supplydemand situation for company's bulld
to stock business model. Your task is to analyze and evaluate the current
demandsupply. You will propose a solution based on your analysls.
a Based on the situation below, analyze the demand pattem. You may use
weeks moving average and visualize Into line graphs. Comment on the trend.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock