Question: b. Complete the Materials Requirements Planning grid below given the following information: Beginning inventory = 2 units Lot Size = 100 units Lead time =

b. Complete the Materials Requirements Planning grid below given the following information: Beginning inventory = 2 units Lot Size = 100 units Lead time = 1 period Safety Stock = 0 units Period 1 2 3 4 5 6 Gross Requirements 20 20 40 30 30 30 Scheduled Receipts 50 Projected Available Balance Planned Order Receipt Planned Order Release
Step by Step Solution
There are 3 Steps involved in it