Question: b Costing Help Save ( ! ) You skipped this question in the previous attempt. On April 1 , two jobs were in process at

b Costing
Help
Save
(!) You skipped this question in the previous attempt.
On April 1, two jobs were in process at Hartwell Contracting. Details of the jobs follow:
\table[[Job,Direct,Direct],[Number,Materials,Labor],[HC-34,$4,200,$1,600
Also during April, Jobs HC-34 and HC-37 were completed. Completing Job HC-34 required an addi completion costs for Job HC-37 included $3,200 in direct materials and $10,500 in direct labor.
Hartwell Contracting used a total of $8,900 of direct materials (excluding the $1,540 indirect materia in total direct labor costs. Overhead has been estimated at 75 percent of direct labor costs, and this past few years.
Required:
Compute the costs of Jobs HC-34 and HC-37 and the balances in the April 30 inventory accounts.
\table[[Cost to complete HC-34,],[Cost to complete HC-37,],[Balance of Materials Inventory as of April 30,],[Balance of Work-in-Process Inventory as of April 30,],[Balance of Finished Goods Inventory as of April 30,]]
Prey
23 of 25
Next
b Costing Help Save ( ! ) You skipped this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!