Question: b) Given the demand, the cycle time for the production of the new train set = ___ seconds (round to two decimals). c) The theoretical

b) Given the demand, the cycle time for the production of the new train set = ___ seconds (round to two decimals).
c) The theoretical minimum number of workstations = ___.
d) The total idle time per cycle for the process = ___ seconds.
e) The efficiency of the assembly line with 5 workstations = ___%. (Round to two decimals).
f) If one used 6 workstations instead of 5, the efficiency of the assembly line would be = ___%. (Round to two decimal places).
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Task Predecessors Performance Time (seconds) 22 27 A B A 14 D 15 A A B, C D, E E F 10 28Step by Step Solution