Question: B. How many weeks will it take to complete the project? C. How much slack does activity B have? The following activities are part of

B. How many weeks will it take to complete the project?
C. How much slack does activity B have?
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR A B TIME (WEEKS) 6 7 2 4 E A A B%media:cm.png% D D E%media:cm.png% F 5 F 3 G 7 a. What is the critical path? A-C-D-F-G A-B-D-F-G A-C-D-E-G A-B-E-GStep by Step Solution
There are 3 Steps involved in it