Question: b. How many weeks will it take to complete the project? c. How much slack does activity B have? The following activities are part of

b. How many weeks will it take to complete the project? c. How much slack does activity B have?
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) Timo OUD 00 mnmm BD D EF a. What is the critical path? A-B-E-G O A-C-D-E-G O A-B-D-F-G O A-C-D-F-GStep by Step Solution