Question: b.) how many weeks will it take to complete the project? c.) how much slack does activity B have? The following activities are part of

b.) how many weeks will it take to complete the project?
c.) how much slack does activity B have?
The following activities are part of a project to be scheduled using CPM: IMMEDIATE PREDECESSOR ACTIVITY B D E F G A C B D D E, F TIME (WEEKS) 6 3 7 2 4 3 7 a. What is the critical path? O A-B-E-G A-C-D-E-G O A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks BR BE 2 of 12Step by Step Solution