Question: (b) How many working minutes (observed time) do you expect would take a worker to produce a part for which: The time standard (based

(b) How many working minutes (observed time) do you expect would take

(b) How many working minutes (observed time) do you expect would take a worker to produce a part for which: The time standard (based on job) is 10 minutes, If the allowance for this work is 25% of the normal time and The worker is rated at 80%?

Step by Step Solution

3.48 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Salution given Standard time Ts 10 minutes TN Normal time To obse... View full answer