Question: (b) How many working minutes (observed time) do you expect would take a worker to produce a part for which: The time standard (based
(b) How many working minutes (observed time) do you expect would take a worker to produce a part for which: The time standard (based on job) is 10 minutes, If the allowance for this work is 25% of the normal time and The worker is rated at 80%?
Step by Step Solution
3.48 Rating (158 Votes )
There are 3 Steps involved in it
Salution given Standard time Ts 10 minutes TN Normal time To obse... View full answer