Question: b - If the required return is 1 0 percent, what is the NPV for each of these projects? ( Do not round intermediate calculations
b If the required return is percent, what is the NPV for each of these projects? Do
not round intermediate calculations and round your answers to decimal places, eg
tableProject AProject B
b
Which project will the company choose if it applies the NPV decision rule?
Project A
Project B
c At what discount rate would the company be indifferent between these two projects?
Do not round intermediate calculations and enter your answer as a percent rounded to decimal places, eg
Discount rate