Question: B . List and briefly explain appropriate examples from the seals ( KEGC ) , C . You are the Operations Managers for the Kingston
B List and briefly explain
appropriate examples from the seals KEGC
C You are the Operations Managers for the Kingston Electrical Gadguce Hurricane Lamps. which is in the middle of a plan to install an assembly line to prodiency in production. The Part of your responsibility is to balance the line to increase efficith their production times work elements to be performed are listed in Table B along with shifts per day and immediate predecessors. The company is planning to oper units per day, hours per shift. The desired output rate of the line is
Table B Data for KEGC
tableTable BData for KEGCWork Element,Time SecondstableImmediatePredecessorsABACBDBEBFCGDHF GIEJHI
Required
I. Draw the network that represents the flow given in Table B
Marks
II Compute and state the cycle time
Mark
III. Compute and interpret the theoretical number of workstations within the context of the problem
Marks
IV Develop a balanced assembly line, using the Longest Processing Time LPT rule, clearly stating the elements in their respective workstations Marks
V Compute the efficiency of the line balanced in IV above
Mark
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock