Question: b ) Materials Requirements Planning ( MRP ) provides a means for scheduling the ordering of raw materials and parts. Part of the Bill of
b Materials Requirements Planning MRP provides a means for scheduling the ordering of raw materials and parts. Part of the Bill of Materials for a vacuum coating machine includes the following structure:
The following ordering details are known about each part:
Part has a lead time of weeks and a Minimum Order Quantity of
Part has a lead time of week and Economic Order Quantity of
Part has a lead time of weeks and a fixed order period of weeks ie there is always weeks between orders.
The gross requirements for part over the following weeks are:
Weeks
Number
of Part
There are scheduled receipts in week of of Part of Part and of Part
Construct the MRP records for all three parts over the tenweek planning horizon. Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock