Question: B. PROJECT SCHEDULING/PROJECT NETWORK The B/E Aerospace Co. is planning to bid on large project for the development of a new communication system for commercial
B. PROJECT SCHEDULING/PROJECT NETWORK
- The B/E Aerospace Co. is planning to bid on large project for the development of a new communication system for commercial planes. The table below shows the activities, times and sequences required.
| Activity | Immediate Predecessors | Time (Weeks) |
| A B C D E F G H | - A A, B A B C, D D, F E, F, G | 4 9 7 4 3 6 3 2 |
- Construct the project network diagram.
- What is the critical path?
- How many weeks will it take to complete the project?
- How much slack time does activity E have?