Question: Time, Please B. Smitty Smith is a project manager for a large consumer electronics corporation. Although she has been with the company only four

Time, Please B. "Smitty" Smith is a project manager for a large

Time, Please B. "Smitty" Smith is a project manager for a large consumer electronics corporation. Although she has been with the company only four years, she has demonstrated an uncanny ability to bring projects in on time, meet technical specifications, and be close to budget. Her latest assignment is a project that will involve merging two existing technologies. She and her team have almost finished developing the proposal that will be presented to a management committee for approval. All that remains to be done is to develop a time estimate for the project. The team has to construct a network diagram for the project. It has three paths. The expected dura- tions and standard deviations for the paths are listed in the following table. Path CASE Expected Duration (weeks) Standard Deviation A 10 4 B 14 2 13 2 C What project durations (in weeks) should Smitty include in the proposal for these risks of not delivering the project on time: 5 percent, 10 per- cent, 15 percent? What are the pros and cons of quoting project times aggressively? Conservatively?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the project duration for different risk levels 5 10 and 15 probability of not meeting the deadline we use the PERT Program Evaluation and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!