Question: b) Suppose that an additional $2,000K is allocated for this project to shorten its completion time. Determine the order of activities to crash (starting from


b) Suppose that an additional $2,000K is allocated for this project to shorten its completion time. Determine the order of activities to crash (starting from the cheapest). Note: you do not have to use the entire allocated budget. B. DA Crash Cost Total cost. AB C E 1 36- 35- 34-33 Step 1 B . $ 200 $ 200 C B C F 1 - 1 33 - 32- 31-30 2 $ 200 $ 400 BB B ABD G 1 39 - 38 - H 3 D $ 250 $ 650 D. 36 -35- ITO $ 250 $ 900 4 400 $ 1300 $ 400 $ 1 1700