Question: b) the average demand during the 8 week lead time is ____ pints c) the reorder point that results in a cycle-service level of 96

b) the average demand during the 8 week lead time is ____ pints
c) the reorder point that results in a cycle-service level of 96 percent is ___ pints
Homework: Problem Set 8 - Inventory Management 2 Score: 0 of 3 pts 3 of 7 (2 complete) HW Score: 13.33%, 2 of Problem 15 Question Help In a Q system, the demand rate for strawberry ice cream is normally distributed, with an average of 305 pints per week. The lead time is 8 weeks. The standard deviation of weekly demand is 16 pints. Refer to the standard normal table for z-values. a. The standard deviation of demand during the 8-week lead time is pints. (Enter your response rounded to the nearest whole number)Step by Step Solution
There are 3 Steps involved in it