Question: b ) The demand for the gear assembly for a period of 1 0 weeks is given below: Week 1 2 3 4 5 6

b) The demand for the gear assembly for a period of 10 weeks is given below:
Week 12345678910
Demand 55654550302043374235
Currently there are 120 gear assemblies on hand. Production is planned by using a fixed order period method of two periods. The lead time is two periods. Determine the planned order release schedule.