Question: B. The variance for activity C is _____ weeks. (Round your response to two decimal places.) C. Based on the calculation of the estimated times,
B. The variance for activity C is _____ weeks. (Round your response to two decimal places.)
C. Based on the calculation of the estimated times, the critical path is _________
D. The estimated time for the critical path is _____ weeks. (Round your response to two decimal places.)
E. The activity variance along the critical path is ______ weeks. (Round your response to two decimal places.)
F. Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 42 weeks or less is _______. (Enter as a probability and round your response to three decimal places.)
a) The expected (estimated) time for activity C is weeks. (Round your responso to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts