Question: (b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years

 (b) Using the completed-contract method, prepare schedules to compute the profitor loss to be recognized as a result of this contract for

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

On March 1, 2020, Sunland Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: Contract costs incurred during the year Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year 2020 2021 2022 $2,683,800 $2,280,200 $2,336,000 3,706,200 2,336,000 -0- 3,180,000 3,500,000 1,720,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g.-45 or parentheses e.g. (45).) 2020 2021 2022

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!