Question: b. What is the minimum total cost associated with completing the project in 15 weeks? c. What is the total time of the minimum-cost schedule?

b. What is the minimum total cost associated with

b. What is the minimum total cost associated with completing the project in 15 weeks?

c. What is the total time of the minimum-cost schedule?

The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity Immediate Predecessor(s) A B Normal Time Crash Time Normal Cost (weeks) (weeks) ($) 3 1 7,000 2 2 3,000 3 1 12,000 4 3 12,000 1 1 8,000 6 4 5,000 3 2 9,000 Crash Cost ($) 14,000 3,000 40,000 22,000 8,000 13,000 16,000 D E F B D, E E G a. What is the shortest time duration for this project regardless of cost? The shortest project duration regardless of cost is weeks. (Enter your response as a whole number.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!