Question: b . What is the probability that the project can be completed in 2 4 days or less? In 2 1 days or less? (

b. What is the probability that the project can be completed in 24 days or less? In 21
days or less? (Round your te and z values to 2 decimal places and "Standard
deviation" to 3 decimal places. Round your final answers to 4 decimal places.)
c. Suppose it is now the end of the seventh day and that activities A and B have been
completed while activity D is 50 percent completed. Time estimates for the
completion of activity D are 5,6, and 7. Activities C and H are ready to begin.
Determine the probability of finishing the project by day 24 and the probability of
finishing by day 21.(Round your intermediate calculations to 3 decimal places and
final answers to 4 decimal places.)
 b. What is the probability that the project can be completed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!