Question: b) What is the total cost required for completing this project on normal time? c) If you wish to reduce the time required to complete
b) What is the total cost required for completing this project on normal time?
c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
The critical path with the longest length through the project is?
To speed up the project at the least additional cost, first crash the activity
that has the lowest crash cost per week. Determine the crash cost per week for each activity on the critical path.
d)
For activity A, the per week crashing cost =
For activity D, the per week crashing cost
For activity G, the per week crashing cost
For reducing the duration of the project by one week, the activity that should be crashed first is activity:
The cost of the project based on the first activity selected for crashing will increase by:
What is(are) the critical path(s) after crashing activity D down to 4 weeks?
Hence, any further crashing must be done to both critical paths.
Determine the crash cost per week for activities on path B - E - G.
For activity B, the per week crashing cost:
For activity E, the per week crashing cost:
For activity G, the per week crashing cost:
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Time (weeks) 4 Activity A B Crash Time (weeks) 3 Normal Cost 2 1 Total Cost with Immediate Crashing Predecessor(s) $2,650 $2,700 $750 $2,600 A $1,450 B $4,400 $2,000 D, E C 3 3 D 8 $2,000 $2,100 $750 $2,300 $1,000 $3,000 $1,600 4 E 6 3 F 2 3 4 G 2 a) Based on the given information regarding the activities for the project, the project length = weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts