Question: b) What would the priorities likely be for this project? [15 MARKS] [5 MARKS] QUESTION 4 The activities, their durations and precedences for a generic

b) What would the priorities likely be for this project? [15 MARKS] [5 MARKS] QUESTION 4 The activities, their durations and precedences for a generic project for testing a project management software are shown in Table Q4. TableQ4generic project Activity Preceding activity Estimate in months Start 0 D Start 4 A Start 6 F D, A 7 D 8 G F, E UI F H G 7 C H End C, B 0 a) By use of network analysis determine is the earliest time that the operation might be completed? [15 MARKS] a) Which of the activities are on the critical path? 15 MARKS]QUESTION 5