Question: BAC = 2 0 0 PV = 1 0 0 AC = 1 2 0 EV = 8 0 Assuming that what the project has

BAC =200
PV =100
AC =120
EV =80
Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion (EAC) is:
375.
300.
325.
350.