Question: BAC = 2 0 0 PV = 1 0 0 AC = 1 2 0 EV = 8 0 Assuming that what the project has
BAC
PV
AC
EV
Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion EAC is: