Question: Balance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an 8-hour
Balance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an 8-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
- Fill in the table below for a shift output of 60 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
| Workstation | Tasks | Total Time | Idle Time |
| 1 | b, e |
|
|
| 2 | a, c, d, g |
|
|
| 3 | h, f, i |
|
|
| 4 | k, j |
|
|
| Total |
|
|
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts