Question: Bananas are processed through a two-step processFirst, the fruit is separated in a machine with a capacity of 1,175 bananas per hour Next, the fruit

Bananas are processed through a two-step processFirst, the fruit is separated in a machine with a capacity of 1,175 bananas per hour Next, the fruit is wrapped with a machine that has a capacity of 825 bananas per hourDemand for bananas exceeds supply a pull system, what will be the utilization of the first machine? Note: Round your answer to 3 decimal places