Question: Base on the critical path; find the probability of completing the office renovation project by 39 days. Find the date by which you would be

Base on the critical path; find the probability of completing the office renovation project by 39 days. Find the date by which you would be 90 percent sure of completing the project.

Base on the critical path; find the probability of completing the office

Step by Step Solution

3.45 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the probability of completing the project within a certain timeframe using the Critical Path Method CPM and the Program Evaluation and Re... View full answer