Question: Base on the data collected by the Lean Six Sigma team, carry out the following analysis: (a) Calculate the Takt Time for the manufacturing operation.

Base on the data collected by the Lean Six Sigma
Base on the data collected by the Lean Six Sigma team, carry out the following analysis:
(a) Calculate the Takt Time for the manufacturing operation.
(b) Calculate the cycle time (in minutes) for the 4 assembly processes.
(c) Assumed that work in progress for all assembly processes is 1 (one). Develop the Takt Time chart for assembly process 1 to 4.
(d) Bases on the Takt Time Chart Developed in (c), propose the next course of action for assembly process 1, 2, 3 and 4? Justify your proposal.
(e) If the value-added time for Process 1 is 8 seconds. Calculate the Process Cycle Efficiency (PCE) for Process 1.
(f) Propose improvement actions for Process 1 bases on PCE calculated in (e). Justify the proposal.
(g) TheLeanSixSigmateamisyettostudytheprocessfromSixSigmaperspective.Propose to the team the Six Sigma target in term of process potential index and process capability index. Explain to the team the two approaches for Six Sigma improvement.
Five Stars Manufacturing Sdn Bhd is a local company that producing portable fan. The portable fans made up of few components and are assembled through 4 assembly process. A Lean Six Sigma team in Five Stars is working on a project to improve assembly process cycle time. Table 1.0 and 2.0 summarize the operation data and cycle time data collected by the Lean Six Sigma team at the project's Measure phase. Tahle 1 nnerational Nata

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!