Question: Based on critical path method, the Earliest Start time is 7 and the Latest End time is 1 1 for activity ( paiting ) .
Based on critical path method, the Earliest Start time is and the Latest End time is for activity paiting Assume that the paiting task takes days. Which of the following statements is not true?
The Latest Start time is
The Earliest Finish is
This activity paiting is not on a critical path
Delaying this activity by days will affect the project duration
None of the above