Question: Based on critical path method, the Earliest Start time is 7 and the Latest End time is 1 1 for activity ( paiting ) .

Based on critical path method, the Earliest Start time is 7 and the Latest End time is 11 for activity (paiting). Assume that the paiting task takes 3 days. Which of the following statements is not true?
The Latest Start time is 8
The Earliest Finish is 10
This activity (paiting) is not on a critical path
Delaying this activity by 1 days will affect the project duration
None of the above