Question: Based on Exercise 18-33 During 2020, Kingbird Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The
| Based on Exercise 18-33 | |||||||||||||||
| During 2020, Kingbird Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. | |||||||||||||||
| 2020 | 2021 | 2022 | |||||||||||||
| Costs incurred to date | $393,900 | $760,380 | $1,059,000 | ||||||||||||
| Estimated costs to complete | 616,100 | 341,620 | 0 | ||||||||||||
| Billings to date | 299,000 | 905,000 | 1,610,000 | ||||||||||||
| Collections to date | 268,000 | 818,000 | 1,421,000 | ||||||||||||
| 2. Prepare journal entries for all 3 years. |
| 2020 | 2021 | 2022 | |
| Contract Price | $1,610,000 | $1,610,000 | $1,610,000 |
| Cost incurred to date | $393,900 | $760,380 | $1,059,000 |
| Estimated cost yet to be incurred to complete the contract | $616,100 | $341,620 | $0 |
| Total cost | $1,010,000 | $1,102,000 | $1,059,000 |
| % of completion | 39% | 69% | 100% |
| Revenue to date | $627,900 | $1,110,900 | $1,610,000 |
| Revenue previous year | $0 | $627,900 | $1,110,900 |
| Net revenue this year | $627,900 | $483,000 | $499,100 |
| Cost to date | $393,900 | $760,380 | $1,059,000 |
| Cost to date of previous year | $0 | $393,900 | $760,380 |
| Net cost of the year | $393,900 | $366,480 | $298,620 |
| Gross Profit | $234,000 | $116,520 | $200,480 |