Question: Based on forecasted needs QUESTION 3 Consider a workstation that can process 3289 units per hour. It takes 15 minutes to receive an order

Based on forecasted needs QUESTION 3 Consider a workstation that can process

Based on forecasted needs QUESTION 3 Consider a workstation that can process 3289 units per hour. It takes 15 minutes to receive an order from the previous station. The container size is 71 units. The factory sets safety stock at 20 percent of demand during lead time. How many Kanbans are needed for the workstation? (Calculate your answer to one decimal place.)