Question: Based on past experience, a manufacturing process requires 2.3 hours of direct labour for each $174 worth of raw materials processed. If the company is
Based on past experience, a manufacturing process requires 2.3 hours of direct labour for each $174 worth of raw materials processed. If the company is planning to consume $78,300 worth of raw materials, what total amount should it budget for labour at $31.50 per hour?