Question: Based on table 2 , ( 1 ) draw AON network diagram. ( 2 ) fill table 3 , find the critical path. ( 3

Based on table 2,
(1) draw AON network diagram.
(2) fill table 3, find the critical path.
(3) fill table 4, draw earliest time Gantt chart on table 4.
(4) draw histogram of earliest time resource load.
 Based on table 2, (1) draw AON network diagram. (2) fill