Question: Based on table below, do the following: Draw the network diagram. Sequence the activities based on the dependency. Using the forward pass, determine ES and
Based on table below, do the following:
- Draw the network diagram. Sequence the activities based on the dependency.
- Using the forward pass, determine ES and EF
- Using the backward pass, determine LS and LF
- Determine the float of each activity
- Determine the activities in the critical path
- Determine the overall duration of the project


Activity Duration Dependency Start 0 {days} A 5 {days} Start B 2 {days} Start C 3 {days} A, B D 5 {days} Start E 6 {days} Start _F 4 {days} D, E G 2 {days} C, F _H 5 {days} G _| 7 {days} G J 3 {days} H Finish 0 {days} |,J Duration ES EF Key: ES = Early start Activity name Amount of float EF = Early finish LS = Late start LS LF LF = Late finish