Question: Based on the activity time estimates, the expected times and variance for each of the activities(A,B,C,D) are _______________________________ (round your response to two decimal places).

Based on the activity time estimates, the expected times and variance for each of the activities(A,B,C,D) are _______________________________ (round your response to two decimal places).
b) The expected completion time of the critical path =
(ans in 2 dp)
The expected completion time of the path other than the critical path =
C the variance of the critical path________
d) If the time to complete the activities on the critical path is normally distributed, what is the probability that this path will be finished in 22
weeks or less?
Compute Z.
Using
the standard normal table
LOADING...
,
the probability that the critical path will be finished in
22 weeks or less = ___________
(enter as a probability and round your response to two decimal places).
e) If the time to complete the activities on the non critical path is normally distributed, what is the probability that this path will be finished in
22 weeks or less?
Compute Z.
Using
the standard normal table
the probability that the non critical path will be finished in
22
weeks or less =
(enter as a probability and round your response to two decimal places).
Part 20
f) The smallest probability across all paths is the probability of project finishing in time.
Based on the probabilities found for the critical path and the other path, the probability that the project will be finished in 22 weeks or less =
enter your response here
(round your response to two decimal places).
Question 6, Problem 3.20 HW Score: 1.25%,0.25 of 20 Part 1 of 10 points Points: 0 of 2 The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent. This exercise contains only parts a,b,c,d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
