Question: Based on the AON chart below, the paths and their durations are C F A 3 6 4 start 0 H B 25 35 E

Based on the AON chart below, the paths and their
Based on the AON chart below, the paths and their durations are C F A 3 6 4 start 0 H B 25 35 E 17 D G 4 6 O A-C-F-H with 20 days and B-D-E-F-H with 25 days O B-D-G-H with 22 days O A-C-F-H with 22 days and B-D-G-H with 22 days O A-C-F-H with 20 days, B-D-E-F-H with 25 days, and B-D-G-H with 22 days none of these