Question: Based on the book, Kerzner, H. (2017). Project Management: A systems approach to Planning, Scheduling, and Controlling (12th ed.). or in PMBOK 7th Edition, answer

Based on the book, Kerzner, H. (2017). Project Management: A systems approach to Planning, Scheduling, and Controlling (12th ed.). or in PMBOK 7th Edition, answer the below question: What project component is the procurement Statement of Work based on? a. The Work Breakdown Structure (WBS) b. The project scope statement c. The WBS dictionary d. The scope baseline