Question: Based on the following activity list, which statement is incorrect? Activity Predecessor Duration A - 5 B A 7 C A 3 D C 5
Based on the following activity list, which statement is incorrect?
Activity Predecessor Duration A - 5 B A 7 C A 3 D C 5 E A 4 F E 4 G B,D,F 2 H G 5
Group of answer choices
Late start of B is 5.
Late finish of A is 5.
Late start of C is 5.
Early start of F is 9.
Step by Step Solution