Question: Based on the following activity precedence relationship a ) Draw the AON and CPM ( Critical Path Method or AOA - Activity on Arrow )

Based on the following activity precedence relationship a) Draw the AON and CPM (Critical Path Method or AOA - Activity on Arrow) network. Clearly label the activities, dummy activities, events, nodes, edges etc. (if any) and follow the network rules; b) Perform forward and backward path calculations including total float, free float, interfering float, and independent float, and clearly show the critical path; c)(BONUS) Assuming one (or many) activities are delayed, is it possible that there will be two or three critical paths? If yes, at what durations, if no, why?
Formula:
TF=LF-EF=LS-ES,FF=ESsuccessoractivities-EFactivity?I
ntF=TF-FF IndF =min(ESsuccessoractivities-LFactivity)
\table[[Activity,Predecessors,Duration (in days)],[A,-,5],[B,-,2],[C,-,4],[D,A,2],[E,A,B,5],[F,A,B,C,3]]2
Based on the following activity precedence

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!