Question: Based on the following information, please develop a project network diagram for the scheduling purpose. Activity Predecessors Duration ES EF LS LF Slack A -
Based on the following information, please develop a project network diagram for the scheduling purpose.
| Activity | Predecessors | Duration | ES | EF | LS | LF | Slack |
| A | - | 2 |
|
|
|
|
|
| B | A | 2 |
|
|
|
|
|
| C | A | 4 |
|
|
|
|
|
| D | B | 2 |
|
|
|
|
|
| E | C | 1 |
|
|
|
|
|
| F | D, E | 2 |
|
|
|
|
|
| G | F | 3 |
|
|
|
|
|
- Use the network diagram, fill in all the empty cells in the table above.
- List all the paths. Also, indicate their durations and path slacks.
- Which path is the critical path? How long does it take to complete the project?