Question: Based on the following information, please develop a project network diagram for the scheduling purpose. Activity Predecessors Duration ES EF LS LF Slack A -

Based on the following information, please develop a project network diagram for the scheduling purpose.

Activity

Predecessors

Duration

ES

EF

LS

LF

Slack

A

-

2

B

A

2

C

A

4

D

B

2

E

C

1

F

D, E

2

G

F

3

  1. Use the network diagram, fill in all the empty cells in the table above.

  1. List all the paths. Also, indicate their durations and path slacks.

  2. Which path is the critical path? How long does it take to complete the project?