Question: Based on the following MPS, BOM, and inventory data, fill out blank MRP tables to answer questions 3 and 4 below. Master Production Schedule: The
Based on the following MPS, BOM, and inventory data, fill out blank MRP tables to answer questions 3 and 4 below.
- Master Production Schedule: The following table shows the MPS release dates already offset for item As lead time.
|
| Week | |||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 |
| MPS |
|
| 60 |
| 60 |
|
- Bill of Material -End item A uses 1 each of component D, 2 each of component C, and 2 each of B.
-Item B uses 1 each of component D and 1 each of component E.
- Selected Inventory Data
|
| Item | ||
| Data Category | B | C | D |
| Lot-sizing rule | L4L | FOQ = 180 | POQ (p = 3) |
| Lead time (weeks) | 2 | 1 | 1 |
| Beginning (on-hand inventory) | 30 | 160 | 50 |
| Safety stock | 0 | 50 | 30 |
| Scheduled receipts | 190 (week 2) | 180 (week 1) | 40 (week 1) |
3. Which of the following statements concerning item B is true?
- The projected on-hand quantity at the end of week 6 is 60 units.
- There are exactly 2 planned order releases.
- The first planned order release occurs in week 3.
- The second planned order release occurs in week 5.
- None of the above.
4. Which of the following statements concerning item D is true?
- The projected on-hand quantity at the end of week 6 is 0 units.
- There are two planned receipts
- The first planned release is 80 units in week 2
- Net requirements in week 3 is zero
- None of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock