Question: Based on the following MPS, BOM, and inventory data, fill out blank MRP tables to answer questions 3 and 4 below. Master Production Schedule: The

Based on the following MPS, BOM, and inventory data, fill out blank MRP tables to answer questions 3 and 4 below.

  1. Master Production Schedule: The following table shows the MPS release dates already offset for item As lead time.

Week

Week

1

2

3

4

5

6

MPS

60

60

  1. Bill of Material -End item A uses 1 each of component D, 2 each of component C, and 2 each of B.

-Item B uses 1 each of component D and 1 each of component E.

  1. Selected Inventory Data

Item

Data Category

B

C

D

Lot-sizing rule

L4L

FOQ = 180

POQ (p = 3)

Lead time (weeks)

2

1

1

Beginning (on-hand inventory)

30

160

50

Safety stock

0

50

30

Scheduled receipts

190 (week 2)

180 (week 1)

40 (week 1)

3. Which of the following statements concerning item B is true?

  1. The projected on-hand quantity at the end of week 6 is 60 units.
  2. There are exactly 2 planned order releases.
  3. The first planned order release occurs in week 3.
  4. The second planned order release occurs in week 5.
  5. None of the above.

4. Which of the following statements concerning item D is true?

  1. The projected on-hand quantity at the end of week 6 is 0 units.
  2. There are two planned receipts
  3. The first planned release is 80 units in week 2
  4. Net requirements in week 3 is zero
  5. None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!