Question: Based on the following table, answer the next questions. The value of for activity D is 11 12 15 18 5 puntos The probability of

Based on the following table, answer the nextBased on the following table, answer the nextBased on the following table, answer the next

Based on the following table, answer the next questions. The value of for activity D is 11 12 15 18 5 puntos The probability of finish the project in 30 days or less is 57%62%70%74% 5 puntos PERT assumes that the duration of each activity is a random variable with unknown mean and standard variation. True False 5 puntos The value of E2 for activity I is .30.45.551.00 5 puntos The Critical Path of the project using is A,C,F,HA,B,F,HA,B,C,F,HA,B,C,F,H,I