Question: Based on the following tables, answer questions a through h. Budget cost: *Numbers are in $thousands Week TBC 1 2 3 4 5 Task 1
Based on the following tables, answer questions a through h.
Budget cost:
*Numbers are in $thousands
| Week | ||||||
| TBC | 1 | 2 | 3 | 4 | 5 | |
| Task 1 | 50 | 25 | 25 | |||
| Task 2 | 30 | 10 | 10 | 10 | ||
| Task 3 | 70 | 40 | 30 | |||
| Task 4 | 20 | 10 | 10 | |||
Actual cost:
*Numbers are in $thousands
| Week | |||||||
| 1 | 2 | 3 | 4 | 5 | |||
| ACTUAL | Task 1 | 25 | 10 | ||||
| COSTS | Task 2 | 10 | 15 | ||||
| Task 3 | 40 | ||||||
| Task 4 | |||||||
Percentage of work complete:
| Week | ||||||
| 1 | 2 | 3 | 4 | 5 | ||
| PERCENTAGE | Task 1 | 60 | 100 | |||
| OF WORK | Task 2 | 50 | 100 | |||
| COMPLETE | Task 3 | 70 | ||||
| Task 4 | ||||||
a. What is the cumulative budgeted cost at the end of week 3?
b. What is the cumulative actual cost at the end of week 3?
c. What is the cumulative earned value at the end of week 3?
| Week | ||||||
| 1 | 2 | 3 | 4 | 5 | ||
| Task 1 | ||||||
| Task 2 | ||||||
| Task 3 | ||||||
| Task 4 | ||||||
| Total | ||||||
d. What is the Cost Performance Index at the end of week 3?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock