Question: Based on the given data, determine the following: Activity Immediate Predecessor Mean Time Variance A - 12 0.11 B - 9 1.78 C A 10

Based on the given data, determine the following:

Activity Immediate Predecessor

Mean Time Variance A - 12 0.11 B - 9 1.78 C A 10 2.78 D B 10 1.78 E B, D 24 7.11 F C,D 10 4 G C,F 35 7.11 H G 40 2.78 I G 15 9

a) Draw AON diagram showing ES, EF, LS and LF? b) What is the critical path, project completion time and project variance c) You have estimated that only 70 % chance the project would have been finished in the said time of the customer. Determine the time the customer is demanding to sign off the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!