Question: Based on the given information regarding the activities for the project, the project length = The total cost required for completing this project on normal

- Based on the given information regarding the activities for the project, the project length =
- The total cost required for completing this project on normal time =
- For reducing the duration of the project by one week, the activity that should be crashed first is activity (a-g)=
The cost of the project based on the first activity selected for crashing will increase by
d) The maximum weeks by which the project can be reduced by crashing =
Total cost of crashing the project to minimum (or maximum weeks possible) =
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A Normal Time (weeks) 4 Crash Time (weeks) 3 2 3 8 1 3 4 3 Normal Cost $2,100 $2,200 $600 $2,400 $800 $3.200 $1,400 Total Cost with Immediate Crashing Predecessor(s) $2,750 $3,000 $600 $2,720 A $1,175 B $4,700 $2,000 DE E 6 3 F G 2 2 4 a) Based on the given information regarding the activities for the project, the project length = weeks. =Step by Step Solution