Question: Based on the information in the table, calculate the NPV for project A. Project B ($43) $30 $10 $20 Year Project A ($175) $75 $75


Based on the information in the table, calculate the NPV for project A. Project B ($43) $30 $10 $20 Year Project A ($175) $75 $75 $50 10.00% 0 2 3 WACC A -S727 O B $7.49 C-$6.91 O D $25.00