Question: Based on the information presented in the following table; Standard Actual Material Cost Per Yard $2.00 $2.10 Yards per Unit 4.5 yards 4.75 yards Units
Based on the information presented in the following table;
| Standard | Actual | |
| Material Cost Per Yard | $2.00 | $2.10 |
| Yards per Unit | 4.5 yards | 4.75 yards |
| Units of Production | 9,500 |
The Direct Materials Price Variance is equal to:
Question 17 options:
| -$4,512.50 Favorable | |
| $4,750.00 Unfavorable | |
| -$4,750.00 Favorable | |
| $4,512.50 Unfavorable |