Question: Based on the information provided in Exhibit 1 3 . 2 how well is the Decommissioning project doing in terms of cost and schedule? What
Based on the information provided in Exhibit how well is the Decommissioning project doing in terms of cost and schedule? What additional information would you like to have in order to assess performance on the project?EXHIBIT
table
tableCostBudget PerformancePortland General Electric CoTrojan Nuclear Plant
tableDecommissioning Cumulative CostsReport Run: JanNominal Year DollarsReport Numbe,: DECTOPage:,, of DescriptionPVEVACYeartoDate,
tableYTDVarianceEVACPVtableCPIEVACtableSPIEVPVPVEVISFSIRVAIREquip removalABFBEquip removalother,Embed pipingABFBEmbed pipingother,Surface deconABFBSurface deconother,Surface deconcontainment,Radwaste disposal,Final survey,Nonradiological areas,StaffingISFSILongterm ops,Labor loadings,Material loadings,Corporate governance,Undistributable costs,Total decommissioning,Total less ISFSI and RVAIR
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock