Question: Based on the information shown in Figure 2, which tasks are on the critical path? Group of answer choices A,E,F,C,G A,B,D,G A,D,F,G A,D,F,C,G A,B,C,G Based

Based on the information shown in Figure 2, which tasks are on the critical path?
Group of answer choices
A,E,F,C,G
A,B,D,G
A,D,F,G
A,D,F,C,G
A,B,C,G
Based on the information shown in Figure 2, what is the earliest day on which the project can finish?
Group of answer choices
24
17
30
29
35
Based on the information shown in Figure 2, what is the latest day on which the project must start?
Group of answer choices
12
15
1
7
5
Based on the information shown in Figure 2, Activities A and B are what type of activities?
Group of answer choices
Parallel or Concurrent
Critical path
Serial
Merge
Burst
Based on the information shown in Figure 2, which activity is a Merge activity?
Group of answer choices
F
C
D
A
B