Question: Based on the IRR method, which of the projects will the company accept? Project A Project B Project C Benchmark 2.5 years 2.7 years 3.4

 Based on the IRR method, which of the projects will the

Based on the IRR method, which of the projects will the company accept? Project A Project B Project C Benchmark 2.5 years 2.7 years 3.4 years 3.5 years 4.5 years 4.6 years Payback Discounted Payback NPV IRR MIRR -$2.5 5.6% 5.4% $5.8 11.2% 7.7% $0.5 8.1% 7.9% Project A, B, and C are independent. All projects have the same degree of risk. The company estimates that its WACC = 4%. Select one: a. A B O b.A.C c. B d. A, B, C e. B, C