Question: Based on the network diagram, answer the following questions (5 marks) 11 20 19 18 19 15 10 F 10 15 21 ABCDEFGH J K

 Based on the network diagram, answer the following questions (5 marks)

Based on the network diagram, answer the following questions (5 marks) 11 20 19 18 19 15 10 F 10 15 21 ABCDEFGH J K L 20 18 18 11 19 15 17 15 21 19 10 10 2.1 What is the estimated duration of the project? - 1 mark 2.2 What is the critical path of the project? - 1 mark 2.3 What is the total float for activity F? - 1 mark 2.4 What is the total float for activity G? - 1 mark 2.5 What is the total float for activity E? -1 mark

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!